ACWA Power Grootvlei Gas to Power (G2P) Project near Secunda, Mpumalanga Province
07 July 2026 | Client: ACWA Power
ACWA Power is looking to develop a Gas to Power (G2P) Project in South Africa linked to the Department of Mineral Resources and Energy’s Gas Independent Power Producer Procurement Programme (GASIPPPP).
The proposed development (Grootvlei G2P) Facility) is east of Secunda Town, within the Goven Mbeki Local Municipality, Gert Sibande District Municipality, Mpumalanga province.
The proposed development will entail the establishment of:
- A 1350 MW G2P facility, including the establishment of an on-site substation and switching station;
- Associated infrastructure including internal access roads and construction laydown areas;
- Overhead transmission lines (OTL) to two alternative substations; and
- Connection to the nearest natural gas pipeline (the ROMPCO Pipeline).
The current process is an Environmental Impact Assessment for the G2P facility, the connection to the ROMPCO pipeline, and associated infrastructure such as the access road and construction laydown area.
SLR Consulting (South Africa) (Pty) Ltd (SLR), an independent firm of Environmental Assessment Practitioners, has been appointed by ACWA Power to manage the integrated environmental authorisation processes.
Status
Notice is hereby given, in terms of the EIA Regulations, 2014 promulgated under NEMA, that the Draft Scoping (DSR) prepared for the above-mentioned project has been made available for a 30-day public review and comment period from 06 July 2026 to 8 August 2026.
A copy of the BID, Non-Technical Summary and Draft Scoping Report available for download.
By providing your personal information to submit a comment, you will be included in the SLR an Interested and Affected Party (I&AP) database, and you consent to SLR managing your information in accordance with the Protection of Personal Information Act 4 of 2013. It is assumed that as an I&AP for this Project you authorise SLR to retain and use your Personal Information as part of a contact database for this and/or other Environmental Impact Assessments (EIA) and that you confirm your acceptance for SLR to contact you regarding this and/or other EIA processes. SLR will not process your Personal Information, other than as permitted or required by EIA processes, or as required by law or public policy. SLR will use reasonable, appropriate security safeguards to protect Personal Information, and to reasonably prevent any damage to, loss of, or unauthorised access or disclosure of Personal Information, other than as required for EIA processes or as required by any Law or public policy. You may request for your Personal Information to be deleted from the I&AP database at any time by contacting SLR.
Draft Scoping Report
- 20260706_ACWA_Grootvlei G2P_Scoping Report Final.pdf
- Appendix A - EAP Declaration and CV.pdf
- Appendix B - Project Team CVs.pdf
- Appendix C - DFFE Screening Tool Report.pdf
- Appendix D1 - Aquatic Biodiversity SSV.pdf
- Appendix D2 - Geotechnical SSVR_Project Site.pdf
- Appendix D2 - Geotechnical SSVR_Rompco Pipeline.pdf
- Appendix D3 - Terrestrial Biodiversity SSV.pdf
- Appendix D4 - Visual Assessment.pdf
- Appendix E - Maps.pdf