Tackling Alberta’s Site Rehabilitation Program: Recap and Recipe for Success

Post Date
01 April 2023
Read Time
2 minutes

In April 2020, the Canadian federal government announced a $1.7 billion investment program to clean up inactive wells in Alberta, British Columbia, and Saskatchewan. In May 2020, the site rehabilitation program (SRP) launched in Alberta, providing grants to perform well, pipeline, and oil and gas site closure and reclamation work. The government of Alberta’s website states the goals for the program as “[getting] Alberta’s specialized oil and gas labour force back to work, [accelerating] site abandonment and reclamation efforts, and quickly [completing] a high volume of environmentally-significant work.”

The benefits were felt around the province. With the project coming to an end this February, Alberta Energy estimated that approximately $1 billion in grant funding has been allocated to more than 500 Alberta-based companies, creating more than 3,700 jobs. SLR was fortunate enough to be a part of it, successfully securing funding for 20 clients at over 200 locations. In just under three years, we completed a tremendous amount of work in the short timeframe.

Looking back at how we navigated the SRP process will help us in the future with handling large volumes of work despite human capital deficits, supply chain issues, pandemic restrictions, regulatory changes or whatever else life is going to throw at us while we are trying to get the job done.

I believe the five main factors leading to our success were as follows:

  1. SLR’s OneTeam approach, where we are able to cross-train staff from various disciplines and locations to complete these scopes no matter where the sites were located.
  2. Strong project management and understanding of scopes and client requirements to ensure sufficient funds were allocated. Thanks to this, and great communication and organization from our clients, all projects were completed on budget and on time.
  3. Strong relationships with First Nations, equipment contractors and subconsultants allowing us to navigate through labour and equipment shortages.
  4. Early engagement with regulators, landowners, clients and subcontractors to ensure seamless operations.
  5. Availability of senior technical experts with robust regulatory knowledge able to handle various issues during the project execution.

As we put some of the busiest couple of years in our business behind us, I can’t help but think that we are bound to see more large volumes of closure projects ahead. Whatever comes next, we’re up for the challenge.

Recent posts

  • Insight

    02 July 2025

    3 minutes read

    Climate Transition Plans: Decarbonisation is only one part of the puzzle

    by James Balik-Meacher


    View post
  • power pylon
    Insight

    01 July 2025

    7 minutes read

    Focus on the power grid – Opportunities and challenges unique to data centre power

    by Peter Lo


    View post
  • Plastic waste
    Insight

    25 June 2025

    5 minutes read

    Preparing for Canada's Federal Plastics Registry: Is your business ready?

    by Melissa Birch, Tarra Tamang


    View post
See all posts